DRAFT — recommendation requiring verification. Not an issued or completed work order.
Work order (draft)
Prempura ghat
Upper Lake
Zone / ward: Assign: ____
Prepared for issue by: Visarjan nodal officer, BMC (role; assumption)
Plan start (set the real issue date when issuing): 11 Oct 2026
Why this ghat
- Dissolved oxygen fell below 4 mg/l in 1 of 18 readings (lowest 3.9 mg/l).
- BOD was above 3 mg/l in 9 of 15 readings.
- pH was outside 6.5–8.5 in 2 of 17 readings.
- Some DO, BOD or pH readings are missing. Missing is not treated as passing; a gap adds a sampling action instead.
Tasks
| # | What | When | Responsible role | Done | Remarks |
|---|---|---|---|---|---|
| 1 | Water sampling Priority pre-immersion sampling before 20 Oct: DO, BOD, pH and total coliform (past readings are missing). Recommendation — verify with MPPCB / CPCB guidelines. | 13–18 Oct | MPPCB regional office, Bhopal(assumed — confirm) | __________ | |
| 2 | Water sampling Test pH before immersion and report the reading to the relevant MPPCB laboratory. Recommendation — verify with MPPCB / CPCB guidelines. | 15–20 Oct | MPPCB regional office, Bhopal(assumed — confirm) | __________ | |
| 3 | Barricading & nets Contain floating material with barricades, nets or booms; consider a liner or temporary pond where applicable. Recommendation — verify with MPPCB / CPCB guidelines. | 15–20 Oct | Assign: ____e.g. Zone engineer (civil) | __________ | |
| 4 | Aeration Start aerators at the immersion zone before immersion and check dissolved oxygen (DO) daily with a portable meter. If DO stays below 4 mg/l before 20 Oct, refer to the officer to review an alternative immersion kund. Recommendation — verify with MPPCB / CPCB guidelines. | 17–27 Oct | Assign: ____e.g. Zone engineer (water works) | __________ | |
| 5 | Cleaning & debris Collect flowers and organic offerings separately before immersion; remove idol remnants and debris after immersion; inspect for drains entering the water body. Recommendation — verify with MPPCB / CPCB guidelines. | 18–22 Oct | Assign: ____e.g. Zone sanitation in-charge | __________ | |
| 6 | Water sampling Collect DO, BOD, pH and total coliform samples one week after immersion. Recommendation — verify with MPPCB / CPCB guidelines. | 27 Oct | MPPCB regional office, Bhopal(assumed — confirm) | __________ |
Where: “Prempura Visarjanghat, Bhopal” · “Prempura ghat, Bhopal” · Location note: ____
Target to report against (27 Oct sample)
- Dissolved oxygen 5 mg/l or more
- BOD 3 mg/l or less
- pH 6.5 to 8.5
- Total coliform 500 MPN/100 ml or less (Not in current data; needs a new test)
Report back to the visarjan nodal officer by ________ (date set by the nodal officer)
- Tick sheet of tasks done
- Photos before and after
- Dates the aerators started and stopped
- Quantity of debris removed, if measured
No cost figures are included in work orders.